Tuesday, November 12, 2013

Started from the Bottom

The work continues.  The foundation forms have been removed, waterproofing completed and the water and sewer lines completed in the basement.  The powder room plumbing has been installed and we now have the garage poured.

 
The basement is graded and the walls are buried (to the point it can be since our lot is on a slant)
 
 
There is gravel in the basement now


Back of the house.  This part of the basement won't be under ground


Plumbing for the basement powder room
  
 
The start of the garage
 
 
 
The week of 11/11 we start framing!  
 
 
Our wood is at the lot waiting for the framing
 
 
So, we are still on schedule to be done by the end of January.  Hopefully the weather will cooperate.  It won't be long before it actually starts to look like a house :)
 

 